Schedule & Updates

Piscataqua River Bridge

Bridge Update – 7/13/20

All six lanes will be open on the Piscataqua River Bridge for at least the next two weeks. Remember: if you’re visiting Maine, please make sure to go to www.maine.gov/covid19/ for details on testing and self-quarantine guidelines for out-of-state visitors.

Bridge Update – 2/21/20

Beginning on Monday, February 24th, the “Maine Ahead” project will begin a new phase of safety improvement work on the Piscataqua River Bridge. Crews will be replacing bridge joints that date back to the original construction of the bridge a half-century ago.

This phase of joint replacement work will require the right travel lane to be closed on the southbound side of the bridge. This closure will restrict the southbound side of the bridge to two lanes. It will not be reopened to three lanes until this phase of the joint replacement work is complete.

In a few weeks, we will begin joint replacement work on the northbound side of the bridge as well. This work will require a similar right travel lane closure on the northbound side. We need to close these lanes to be able to work on the bridge joints. These traffic restrictions are also necessary for the safety of our crews and the traveling public.

We hope to be able to reopen these travel lanes as soon as this phase of the bridge joint replacements is complete, but these traffic restrictions could last through mid-May. We are committed to keeping three lanes of travel open on both sides of the bridge during peak travel periods (between mid-May and the day after Labor Day).

We continue to appreciate the patience and understanding of the members of the traveling public as we work on these important safety improvements.

 

Bridge Update – 10/21/19

TRAFFIC UPDATE:
The Southbound right lane on the Piscataqua River Bridge will be closed from 6am on Monday, October 21st through 2pm on Friday, October 25th. A Northbound lane will also be closed from the NH side of the bridge through mile marker 2, as well as the exit 7 entrance ramp, from 9pm through 7am each night through 10/25.

Additionally, we will be closing the Exit 1 off-ramp in Maine beginning on Thursday, October 24th. This ramp will remain closed for the duration of the project which is projected to be substantially complete in October of 2021.

Thank you for your patience!

Bridge Update – 10/15/19

LANE CLOSURE: A southbound lane on the Piscataqua River Bridge will be closed from 6am on Wednesday, October 16th through 2pm on Friday, October 18th. The Exit 7 entrance ramp to I-95 Northbound will also be closed on Wednesday Night (10/16) to layout pavement markings & barrier.

From 9pm through 7am, an I-95 northbound lane will also be closed from the NH side of the bridge through mile marker 2. These closures will occur on Tuesday, Wednesday, Thursday and Friday nights (October 15th-18th) to install traffic signs and pavement markings. Thank you for your patience!

Bridge Project Update 8/2/2019

TRAFFIC UPDATE: During the week of August 4th,  crews will be closing one lane on I-95 from Mile 2 southbound across the Piscataqua River Bridge. The lane closure will be AT NIGHT ONLY (from 7 pm – 5 am) Monday through Thursday. Hydro demolition begins this week, which unfortunately is a noisy process. This will continue for two weeks.  After those two weeks, only regular construction noise is anticipated.  We apologize for the inconvenience.

Bridge Project Update 6/13/19

The Exit 1 southbound on-ramp at Dennett Road in Kittery will be closed indefinitely beginning Tuesday, June 18th at 7 p.m. This is being done to accommodate the work on the Piscataqua River Bridge. In addition, the following lane closures will take place on the Piscataqua Bridge the week of June 17th. 

There will be lane closures Monday through Friday nights starting at 7 p.m. and going until 3:30 a.m. the following morning. The lane closures will be in the southbound lanes only. By 7 p.m., traffic may be restricted to two lanes and by 10 p.m., traffic could be restricted to one lane.

The contractor will be re-stripping the lanes from Exit 2 in Maine and across the bridge to the New Hampshire side. During these hours, the contractor will also be installing temporary concrete barriers to close the shoulder on the Maine approach to the bridge.

Bridge Project Update 6/17/19

We will begin setting up traffic control devices and adding temporary striping, with the assistance of the Maine and/or New Hampshire State Police

Bridge Project Update 6/10/19

We will begin installing signs and setting up message boards with the assistance of the Maine and/or the New Hampshire State Police

Bridge Project Update 5/27/19

Working on access to the site on the Kittery side

Bridge Project Update 5/15/2019

Work is expected to begin in June. Check back for more details soon!

York Toll Plaza

Plaza Project Update – 7/17/20

construction workers
Verifying bottom of slab grades for the toll booth in cash lane #3, south bound.

Contractor:    Reed & Reed, Inc.

Project Schedule: Completion date June 21, 2021.

Progress to Date:  Crews are currently installing granite curb around island 4, forming the curtain wall in lane 16, and have excavated for the canopy columns in lane 3.  The stormwater ponds were recently loamed and seeded and are complete.  Outside the cash lanes, paving crews are placing base and intermediate pavement layers in shoulder areas and in guardrail widening locations north of the toll plaza.   TransCore is working on their newly installed equipment in the ORT lanes.  They have started their initial commissioning.

Plaza Project Update – 3/25/20

Contractors Reed & Reed and RJ Grondin continue to make progress on the new Open Road Toll Plaza in York. Check out what they have been up to.

In the first photo Reed is assisting Grondin as they set the first of the 6 ½ foot tall precast concrete barrier. These barrier segments are too heavy for their excavator requiring a crane for placement. When put in service this barrier will provide positive separation between the southbound cash lanes and the ORT lanes. In the second photo, Grondin is assisting Reed & Reed cast a light pole (LP) barrier segment. This section of LP barrier serves to separate and illuminate the northbound ORT lanes and cash lanes.

 

Construction Work

Construction crane

Plaza Project Update – 2/28/20

The contractor continues to install precast barrier along the ORT lanes and cash lanes.  The NB ORT structure is in place and getting data lines pulled into the conduits.  The SB ORT structure should be going up into place in the next couple weeks, if the weather stays mild.  The contractor continues to make progress inside and outside the toll building.  Outside the building, crews are wrapping up the final trim pieces for the metal roof.  On the inside, electrical, finish plumbing, painting, millwork, data, painting, and ceiling crews are working to bring the interior of the building towards a finished product.  The contractor plans to start firing up the systems within the building in the beginning of March.

 

 

Plaza Project Update – 1/27/20

Reed and Reed placed the south bound ORT slab the first week of the new year. Since then, their crews have been working on adjacent concrete foundations and footings for the overhead tolling structures and other adjacent work. Their sub-contractors have been working on median barrier, drainage, and the toll building. Inside the building, crews are hanging and taping drywall, installing duct work, running communication and electrical wires, and starting to paint as rooms are roughed in. The water has been connected to the building and we are waiting for CMP to connect the building to permanent power. Inside the tunnel, electricians are running wires and working on electrical panels.

Concrete Barrier Construction
R.J. Grondin crew installs precast concrete median barrier south of the new ORT. (Looking south)

Plaza Project Update 12/17/19

Contractor Schedule: The contractor continues to install drilled shafts for the toll system and light poles inside the construction zone.  Crews placed the northbound ORT (Open Road Tolling) concrete slab recently and are preparing to place the southbound slab the week of December 23rd.  Inside the toll building, many trades are working on rough in plumbing, HVAC, and electrical systems.  Concurrently, crews are building walls, installing insulation, and hanging sheetrock.  On the outside, the roofing contractor has been working on the soffit trim.  Reed & Reed is working on traffic control items in between storm events and cold temperatures.

Plaza Project Update 12/17/19

Plaza Project Update – 10/14/19

LANE CLOSURE: Beginning at 6PM on Tuesday, October 15, the York Toll Plaza construction zone at mile 10 on the mainline of the Turnpike will be down to two lanes of traffic in each direction. This traffic pattern will remain in effect for approximately one month while construction crews complete roadway widening and drainage work that will allow for three lanes of traffic during the second phase of the project. Thank you for your patience.

Plaza Update – 10/1/19

TRAFFIC ALERT: Beginning on Tuesday (10/1) through Thursday (10/3) we will be conducting blasting at the new York Toll Plaza. The blasting will occur up to 2 times per day between the hours of 10am and 2pm. During blasting, traffic will be stopped temporarily in both directions at Mile 7.5 Northbound and Mile 10 Southbound. The stoppage will be very short in duration, but please keep in mind that you may experience a brief delay if you’re traveling through this area during the potential blast hours.

Plaza Project Update – 8/20/19

TRAFFIC UPDATE: Beginning tonight (Tuesday, August 19th) northbound traffic at the York Toll Plaza project at Mile 8.8 will be shifted from its current location to the recently constructed outside lanes. While the switchover is taking place on Tuesday night, traffic will go down to one lane (after 11 PM). This will allow crews to switch the lane striping and relocate barrels and barriers. Once this work is complete (before the Wednesday AM commute), they will reopen traffic to all three lanes. Please note that these lanes will be narrowed from 12 feet to 11 feet and speeds will be reduced from 60 MPH to 50 MPH – please drive safely.

Plaza Project Update – 7/19/19

Toll Plaza Cash Lane Area
Paving northbound – looking at toll plaza cash lane area

Percent Complete last approved pay estimate: 22.75%

Contractor Schedule: Reed & Reed completed paving northbound for phase 1 and will begin paving southbound. They completed the closure pour between the tunnel sections and the building foundation. Over the next several weeks they will pave southbound, back fill the building, set the building first floor joists and column, install light pole foundations and street lighting conduit runs. They will also begin setting temporary concrete barrier northbound, loam side slopes in preparation to switch the northbound traffic into phase two mid-September.

Plaza Project Update – 6/24/19

Reed & Reed has set all sections of the tunnel for the first phase of the project.  They have installed several sign foundations and are currently working on the toll building foundation.

RJ Grondin continues to place, grade, and compact Type A gravel.

Pike Industries has started north bound base paving in locations where the Type A gravel has been finished.  Paving and foundation work will continue for the next few weeks.

Based on Reed and Reed’s latest schedule expect traffic to be moved to the new outside lanes sometime in early September so work can begin on median highway speed lanes.

Plaza Project Update 5/17/19

Contractor: Reed & Reed, Inc.
Bid Amount: $39,484,431
Percent Complete last approved pay estimate: 14%
Project Schedule: Completion date June 21, 2021
Contractor Schedule: Reed & Reed set the first give pieces of the pre-cast tunnel on the north-bound side. They are preparing to start foundation work for the toll building and are working on sign foundations on the northern end of the project. RJ Grondin continues to process blasted ledge for gravel and is placing type A gravel in anticipation of final grading and base paving in many locations. They continue to install conduit along the access roadway prior to the utility connections. RJ Grondin continues to install pipe extensions in several locations as they widen slopes along the project.

Plaza Project Update 4/22/2019

Contractor removing blasted ledge from the NB plaza approach

 

Contractor:    Reed & Reed, Inc.

Bid Amount: $ 39,484,431

Percent Complete last approved pay estimate:     11%

Project Schedule: Completion date June 21, 2021.

Project Update: Reed & Reed has completed blasting for the widening areas, the tunnel, and the toll building.  RJ Grondin continues to process blasted ledge for gravel to be used on site.  Pre-cast tunnel sections will be arriving by the end of April.  Contractor plans to install the tunnel sections as soon as they arrive on site.

Project Plaza Update 3/26/19

Rock drill rig

 

Contractor:    Reed & Reed, Inc.

Bid Amount: $ 39,484,431

Percent Complete last approved pay estimate:     11%

Project Schedule: Completion date June 21, 2021.

Contractor Schedule: Reed & Reed continues to blast ledge; they are expecting to be done with the production blasting by the end of April. They will continue with some spot blasting into May. RJ Grondin, earth subcontractor, continues to excavate and backfill gravel on the shoulders. Over the next several weeks, they will continue shaping the access road, install underground utilities, blasting and gravel work.

Plaza Project Update 2/19/19

Box cutting shoulder and back filling with gravel

 

Contractor:    Reed & Reed, Inc.

Bid Amount: $ 39,484,431

Percent Complete last approved pay estimate:     6%                       

Project Schedule: Completion date June 21, 2021. 

Contractor Schedule: Reed & Reed completed installation of the relocated water line. They continue to blast ledge, crush the rock into gravel and boxcut the shoulder and install gravel. This work will continue for the next few months.

Plaza Project Update 1/17/2019

Installing waterline

 

Contractor:    Reed & Reed, Inc.

Bid Amount: $ 39,484,431

Percent Complete last approved pay estimate:     4.6%

Project Schedule: Completion date June 21, 2021.

Project Update: Reed & Reed completed blasting ledge on the access road and began crushing rock to make gravel for the project. Blasting will continue, adjacent to the mainline, for the next couple of months. They are planning to perform two blasts a day between 9am and 2pm. They are scheduled to have the waterline relocated for the York Water District before February. Reed and Reed’s subcontractor, RJ Grondin and Son has been busy box cutting shoulder gravel; they have approximately 24 trucks on site.

Plaza Project Update 12/14/2018

Access Road looking toward Turnpike from Chases Pond Road

 

Contractor:    Reed & Reed, Inc.

Bid Amount: $ 39,484,431

Percent Complete last approved pay estimate:     0%

Project Schedule: Completion date June 21, 2021.

Project Update: Reed & Reed has been blasting ledge for the new relocation of the water line for the York Water District. They plan to begin blasting ledge for the new access road from Chases Pond Road to the toll administration building the week of 16th, this blasting will not require any turnpike stops until they are within 300 feet of the highway. The clearing operation is completed. Reed & Reed will begin constructing the new embankments for the new cash lanes.

Plaza Project Update 11/9/2018

Top of the knoll will be the future toll plaza

 

Contractor:    Reed & Reed, Inc.

Bid Amount: $ 39,484,431

Percent Complete last approved pay estimate:     0%

Project Schedule: Completion date June 21, 2021.

Project Update: Reed & Reed has mobilized on site and began flagging clearing limits. Over the next several weeks, they are planning to clear the access road between the turnpike and Chases Pond Road, new waterline relocation and adjacent to the turnpike. They will remove the stumps and soil over the ledge. They are currently planning to begin blasting ledge the beginning of December and it is expected to continue until March.

Watch the progress!

Sign up for Traffic Alerts from MyTrips New England 511.

Sign Up